The Grand Tortue Ahmeyim gas field
      BUILDING THE DEEPEST



      SUBSEA STRUCTURE




      IN AFRICA






































                                       Carrières
                                     Quarry at
                                     Hajar Denben
                                   275km
                               Port of Nouakchott
                                Port Nouakchott
                      Breakwater
                                                                                           Landing page:
                       Gas         MAURITANIA
                       field                                                               eiffagegeniecivil.com/projects
                    Champs                                                                 Video:
                                                                                           youtube.com/
                        Hub/Stockage caissons
                           SENEGAL                                                         watch?v=pPDGXBhom1Y
                         Port Dakar

      Off the coastlines of Senegal and Mauritania is the       a natural gas storage and export FLNG vessel can begin
      Grand Tortue Ahmeyim gas field. At nearly three           extraction, a protective breakwater must be built.
      kilometers deep, it could produce an estimated            Contractor Eiffage Génie Civil Marine is charged with creating
      15 trillion cubic feet of natural gas. That’s enough      that breakwater. At 10 kilometers from the shore, it will consist of
      for 30 years of production and to make the two            a subsea riprap foundation and giant caissons that can handle
      countries autonomous in terms of energy.                  the highly stressful, ultra-deep-water conditions and sea swells
                                                                that could damage the FLNG vessel and disrupt production.

            “This is a major project for Senegal and Mauritania, and the first   To deliver the material required for the underwater
            step toward becoming more energy independent,” said Thibault   embankment a fleet of Cat  equipment is needed, including
                                                                                    ®
            Seneclauze, Key Account Manager with Cat dealer JA Delmas. “It   about 8 excavators and 16 wheel loaders equipped with
            will certainly improve quality of life and present new opportunities.”  the new Cat Advansys™ ground engaging tools.
            Petroleum company BP has teamed with Mauritania,    “A newly established quarry will provide the 2.5 million tons
            Senegal and Kosmos Energy to recover the liquified natural   of solid granitic gneiss rocks needed for the foundation,”
            gas (LNG). However, before a new offshore complex and   said Hervé Marlenc, Quarry Manager at Eiffage Génie


      8  Cat Magazine