x 21                         Total weight per caisson:
                          31m                               16,200 tons


          28m         55m                Breakwater: 1,150m

                                                                                                   An overview of
                                                                                                   the Grand Tortue
                                                                                                   Ahmeyim project site.
                                                                                                   The processing and
                                                                                                   storage infrastructure
                                                                                                   is 10km out to sea,
                                                                                                   near the Senegal and
                                                                                                   Mauritania border.





                                                                          2.3 million tonnes
                                                                23x
                                                                10  5     per annum of FLNG
                                                                          annual average





















         3x 374 F2 excavators                                             Riprap foundation:
         5x 349 D2L excavators                                            2.5 million tonnes of solid
         7x 986K wheel loaders                                            granitic gneiss rocks
         9x 980L wheel loaders
         1x 140K motor grader                                             Dealer support:
         2x D8R dozers                                         365        Assistance seven
         1x CS78B compactor                                               days a week
         9x Cat generator sets




       Civil Marine. “We also created a stockpile at the port   days a week and monitor machine health through VisionLink,”
       of Nouakchott for loading ships. With such a complex   explained Christophe Courtet , Technical Manager of Mauritrac.
       operation, we depend on Cat VisionLink™ to help manage
       fuel consumption and machine efficiency at each site.”  “This project presents its own unique challenges,” said
                                                           Marcel Parat, After Sales Manager. “As the only heavy
       Cat excavators extract the rock from the quarry first. The   equipment dealer in Mauritania with a physical presence,
       material is then transported to Nouakchott. Local companies   we were able to build on our partnership with Eiffage and
       ultimately deliver the rock to the port where it can be loaded   help streamline complicated stock supply chains.”
       onto ships. The weight of the subcontractors’ road trucks is
       checked before transport. Therefore, each wheel loader is   Hervé agreed. “We have built an environment of trust. This is a
       equipped with Cat Payload™, and we create daily, customized   one-of-a-kind project. We should all be proud – especially about
       reports to maintain accuracy,” precises Thibault Sénéclauze.  opening a quarry and transporting so much material so far.” ■

       “Because the quarry is in the middle of the desert, there is a
       constant battle with heat, sand and dust. To help keep operations
       running smoothly, Mauritrac and JA Delmas have partnered with
       Caterpillar Job Site Solutions (JSS) to provide assistance seven